터널천단변위와 암석 또는 암반의 일축압축강도를 이용한 시공 중인 터널의 예비 안정성 평가
* 본 문서는 배포용으로 복사 및 편집이 불가합니다.
서지정보
ㆍ발행기관 : 한국도로학회
ㆍ수록지정보 : 한국도로학회논문집 / 17권 / 6호
ㆍ저자명 : 박영화, 문홍득, 하만복
ㆍ저자명 : 박영화, 문홍득, 하만복
목차
1. 서론2. 한계변형률 개념
3. 한계변형률을 이용한 터널 예비 안정성평가
4. 결론
감사의 글
REFERENCES
영어 초록
PURPOSES: It is difficult to estimate tunnel stability because of lack of timely information during tunnel excavation. Tunnel deformability refers to the capacity of rock to strain under applied loads or unloads during tunnel excavation. This study was conducted to analyze a methods of pre-evaluation of stability during tunnel construction using the critical strain concept, which is applied to the results of tunnel settlement data and unconfined compression strength of intact rock or rock mass at the tunnel construction site.METHODS: Based on the critical strain concept, the pre-evaluation of stability of a tunnel was performed in the Daegu region, at a tunnel through andesite and granite rock. The critical strain concept is a method of predicting tunnel behavior from tunnel crown settlement data using the critical strain chart that is obtained from the relationship between strain and the unconfined compression strength of intact rock in a laboratory.
RESULTS: In a pre-evaluation of stability of a tunnel, only actually measured crown settlement data is plotted on the lower position of the critical strain chart, to be compared with the total displacement of crown settlement, including precedent settlement and displacement data from before the settlement measurement. However, both cases show almost the same tunnel behavior. In an evaluation using rock mass instead of intact rock, the data for the rock mass strength is plotted on the lower portion of the critical strain chart, as a way to compare to the data for intact rock strength.
CONCLUSIONS : From the results of the pre-evaluation of stability of the tunnel using the critical strain chart, we reaffirmed that it is possible to promptly evaluate the stability of a tunnel under construction. Moreover, this research shows that a safety evaluation using the actual instrumented crown settlement data with the unconfined compression strength of intact rock, rather than with the unconfined compression strength of a rock mass in the tunnel working face, is more conservative.
참고 자료
없음"한국도로학회논문집"의 다른 논문
- 실 규모 터널 주행실험을 통한 터널 경계부 휘도 기준의 적정성 검증11페이지
- 도로전광표지를 이용한 국도우회정보 제공이 고속도로 운영에 미치는 효과 분석 -영동고속도로를 중심으로..8페이지
- 고속도로 오르막차로 교통사고 심각도 영향요인 분석11페이지
- 존별 특성을 반영한 교통사고밀도 모형 - 청주시 사례를 중심으로 -9페이지
- Random Parameter를 이용한 4지 신호교차로에서의 교통사고 예측모형 개발 : 부산광역시를..9페이지
- Laboratory Performance Evaluation of Recycled Asphalt B..9페이지
- 표면 에너지 원리를 이용한 칩실 포장의 초기 점착력 특성 연구8페이지
- 콘크리트 모듈러 도로 축하중 거동 분석을 통한 설계 타당성 검증9페이지
- 차량 이동궤적 기반 버스정차대 기하구조 연구4페이지
- 무기계 바인더를 이용한 탄소저감형 흙포장의 성능평가8페이지